(Construction)
The project was a two phased development on an existing brownfield site, the first phase involved construction of an estate road and a reinforced raft for McDonalds and external works. Highway retaining structures and Lidl were constructed in the second phase. (Duration: 12 Months)
Asphalt and Macadam Surfacing
Bulk Earthworks
Concrete Structures
Foulwater Drainage Systems
Local Authority Adoptable Highway Access Work Sections 106 38 and 278
Reinforced Concrete Raft
Retaining Structures
Street Furniture Installation
Surface Water Drainage Systems